kiro-spec-tasks
Generate implementation tasks from requirements and design. Use when creating actionable task lists.
/plugin install growidetails
kiro-spec-tasks Skill
Core Mission
- Success Criteria:
- All requirements mapped to specific tasks
- Tasks properly sized (1-3 hours each)
- Clear task progression with proper hierarchy
- Natural language descriptions focused on capabilities
- A lightweight task-plan sanity review confirms the task graph is executable before
tasks.mdis written
Execution Steps
Step 1: Gather Context
If steering/spec context is already available from conversation, skip redundant file reads. Otherwise, load all necessary context:
-
.kiro/specs/{feature}/spec.json,requirements.md,design.md -
.kiro/specs/{feature}/tasks.md(if exists, for merge mode) -
Core steering context:
product.md,tech.md,structure.md -
Additional steering files only when directly relevant to requirements coverage, design boundaries, runtime prerequisites, or team conventions that affect task executability
-
Determine execution mode:
sequential = (sequential flag is true)
Validate approvals:
- If auto-approve flag (
-y) is true: Auto-approve requirements and design in spec.json. Tasks approval is also handled automatically in Step 4. - Otherwise: Verify both approved (stop if not, see Safety & Fallback)
Step 2: Generate Implementation Tasks
- Read
rules/tasks-generation.mdfrom this skill's directory for principles - Read
rules/tasks-parallel-analysis.mdfrom this skill's directory for parallel judgement criteria - Read
.kiro/settings/templates/specs/tasks.mdfor format (supports(P)markers)
Parallel Research
The following research areas are independent and can be executed in parallel:
- Context loading: Spec documents (requirements.md, design.md), steering files
- Rules loading: tasks-generation.md, tasks-parallel-analysis.md, tasks template
After all parallel research completes, synthesize findings before generating tasks.
Generate task list following all rules:
- Use language specified in spec.json
- Map all requirements to tasks and list numeric requirement IDs only (comma-separated) without descriptive suffixes, parentheses, translations, or free-form labels
- Ensure all design components included
- Verify task progression is logical and incremental
- Ensure each executable sub-task includes at least one detail bullet that states what "done" looks like in observable terms
- Keep normal implementation tasks within a single responsibility boundary; if work crosses boundaries, make it an explicit integration task
- Apply
(P)markers to tasks that satisfy parallel criteria when!sequential - Explicitly note dependencies preventing
(P)when tasks appear parallel but are not safe - If sequential mode is true, omit
(P)entirely - If existing tasks.md found, merge with new content
Step 3: Review Task Plan
- Keep the draft task plan in working memory; do NOT write
tasks.mdyet - Run the
Task Plan Review Gatefromrules/tasks-generation.md - Review coverage:
- Every requirement ID appears in at least one task
- Every design component, contract, integration point, runtime prerequisite, and validation concern is represented
- Review executability:
- Each sub-task is an executable 1-3 hour work unit
- Each sub-task has a verifiable deliverable
- Each executable sub-task includes an observable completion bullet
- No implicit prerequisites remain hidden
_Depends:_,_Boundary:_, and(P)markers still match the dependency graph and architecture boundaries
- If issues are task-plan-local, repair the draft and re-run the review gate before writing
- Keep the review bounded to at most 2 repair passes
- If review exposes a real requirements/design gap or contradiction, stop and send the user back to requirements/design instead of inventing filler tasks
Step 3.5: Run Task-Graph Sanity Review
Before writing tasks.md, run one lightweight independent sanity review of the task graph.
- If fresh subagent dispatch is available, spawn one fresh review subagent for this step. Otherwise perform the same review in the current context.
- Provide only file paths, the draft task plan, and merge context if an existing
tasks.mdis being updated. The reviewer should readrequirements.md,design.md, and the task-generation rules directly instead of relying on a parent-synthesized coverage summary. - Check only:
- hidden prerequisites or missing setup tasks
- dependency or ordering mistakes
- boundary overlap or ambiguous ownership between tasks
- tasks that are too large, too vague, cross boundaries without being explicit integration tasks, or are missing a verifiable deliverable
- contradictions introduced between requirements, design, and the task graph
- Return one verdict:
PASSNEEDS_FIXESRETURN_TO_DESIGN
- If
NEEDS_FIXES, repair the draft once and re-run the sanity review one time. - If
RETURN_TO_DESIGN, stop without writingtasks.mdand point back to the exact gap in requirements/design. - Keep this bounded. Do not turn it into a second full planning cycle.
Step 4: Finalize
Write tasks.md:
- Create/update
.kiro/specs/{feature}/tasks.md - Update spec.json metadata:
- Set
phase: "tasks-generated" - Set
approvals.tasks.generated: true, approved: false - Set
approvals.requirements.approved: true - Set
approvals.design.approved: true - Update
updated_attimestamp
- Set
Approval:
- If auto-approve flag (
-y) is true:- Set
approvals.tasks.approved: truein spec.json - Display task summary (task count, major groups, parallel markers)
- Respond: "Tasks generated and auto-approved. Start implementation with
/kiro-impl {feature}"
- Set
- Otherwise (interactive):
- Display a summary of the generated tasks (task count, major groups, parallel markers)
- Ask the user: "Tasks generated. Approve and proceed to implementation?"
- If the user approves:
- Set
approvals.tasks.approved: truein spec.json - Respond: "Tasks approved. Start implementation with
/kiro-impl {feature}"
- Set
- If the user wants changes:
- Keep
approvals.tasks.approved: false - Respond with guidance on what to adjust and re-run
- Keep
Critical Constraints
- Task Integration: Every task must connect to the system (no orphaned work)
- Boundary annotations: Required for
(P)tasks, recommended for all (_Boundary: ComponentName_) - Explicit dependencies: Cross-boundary non-obvious dependencies declared with
_Depends: X.X_ - Executable deliverable granularity: Each task must produce a verifiable deliverable (file, endpoint, UI component, config). Infrastructure tasks (project scaffolding, manifest, host integration, build config) must be explicit — never assume they exist
- Observable done state: Each executable sub-task must include at least one detail bullet that makes the completed state visible without adding new bookkeeping fields
- No implicit prerequisites: If a task requires a runtime, SDK, framework setup, or config file, that setup must be a separate preceding task
Output Description
Provide brief summary in the language specified in spec.json:
- Status: Confirm tasks generated at
.kiro/specs/{feature}/tasks.md - Task Summary:
- Total: X major tasks, Y sub-tasks
- All Z requirements covered
- Average task size: 1-3 hours per sub-task
- Quality Validation:
- All requirements mapped to tasks
- Design coverage and runtime prerequisites reviewed
- Task dependencies verified
- Task plan review gate passed
- Independent task-graph sanity review passed
- Testing tasks included
- Next Action: Review tasks and proceed when ready
Format: Concise (under 200 words)
Safety & Fallback
Error Scenarios
Requirements or Design Not Approved:
- Stop Execution: Cannot proceed without approved requirements and design
- User Message: "Requirements and design must be approved before task generation"
- Suggested Action: "Run
/kiro-spec-tasks {feature} -yto auto-approve all (requirements, design, and tasks) and proceed"
Missing Requirements or Design:
- Stop Execution: Both documents must exist
- User Message: "Missing requirements.md or design.md at
.kiro/specs/{feature}/" - Suggested Action: "Complete requirements and design phases first"
Incomplete Requirements Coverage:
- Warning: "Not all requirements mapped to tasks. Review coverage."
- User Action Required: Confirm intentional gaps or regenerate tasks
Spec Gap Found During Task Review:
- Stop Execution: Do not write a patched-over
tasks.md - User Message: "Requirements/design do not provide enough clear coverage to generate an executable task plan"
- Suggested Action: "Refine requirements.md or design.md, then re-run
/kiro-spec-tasks {feature}"
Template/Rules Missing:
- User Message: "Template or rules files missing in
.kiro/settings/" - Fallback: Use inline basic structure with warning
- Suggested Action: "Check repository setup or restore template files"
- Missing Numeric Requirement IDs:
- Stop Execution: All requirements in requirements.md MUST have numeric IDs. If any requirement lacks a numeric ID, stop and request that requirements.md be fixed before generating tasks.
Next Phase: Implementation
Tasks are approved in Step 4 via user confirmation. Once approved:
- Autonomous implementation:
/kiro-impl {feature} - Specific tasks only:
/kiro-impl {feature} 1.1,1.2
technical